A waste water treatment plant with a capacity of 4,980 cubic meters per day was launched.

A waste water treatment plant with a capacity of 4,980 cubic meters per day was launched.

In December, the commissioning of the treatment facilities for household wastewater in the city of Berezino was completed. The capacity of the sewage treatment plant is 4,980 cubic meters per day.
Commissioning took 20 working days. During this time, all equipment was set up, equipment was tested in various modes. 400 cubic meters of activated sludge was brought in for the operation of the treatment facilities.