Start of commissioning works at the wastewater treatment plant in Berezino.

Start of commissioning works at the wastewater treatment plant in Berezino.

The construction phase of the sewage treatment plant in Berezino has been completed. All equipment is mounted and connected. Starting from 1st of December, commissioning work began. There are going djustment of separated equipment, as well as the entire complex as a whole. Activated sludge is delivered to the object.
The capacity of the treatment facilities is 4 980 cubic meters per day.